Aluminium raw material - delivery times more than 20 weeks

Even if we now have to repeat our messages to our customers several times: Please plan for increased replacement times for aluminium items. The raw material not only becomes more expensive, it is also no longer available at normal delivery times. Be sure to schedule an extended replenishment for up to 5 months for security. We now encounter delivery times that are between 16 and 20 weeks higher than normal, depending on the manufacturing process and the exact material specification. Hopefully you can react early enough and know what it needs.

Please contact us. We are trying to find a solution.

Your Sundwiger.

P.S.: There are also further increases in other raw materials. - Please do not forget.